Infrastructure · CL SOLID carbon bridge hangers
Oderbrücke.
Connecting the past
to the future.
88 Carbo-Link carbon hangers support a 130-metre network arch across the Oder, connecting Germany and Poland.
Opened in 2024, the award-winning railway bridge demonstrates how a lightweight hanger system can help reduce material demand across the wider structure and simplify installation.
88
CFRP hangers
130m
Main arch span
4 days
Hanger installation
2024
Bridge opened
The project
A historic route.
A new structural approach.
The crossing between Küstrin-Kietz and Kostrzyn forms part of the historic Prussian Eastern Railway. Its replacement strengthens a regional and freight connection between Germany and Poland.
The new 266-metre superstructure combines a 130-metre network arch with an eastern approach. It accommodates two railway tracks, is designed for speeds up to 120 km/h and makes provision for future electrification.
The challenge
The project team needed to replace an aging crossing while preserving an elegant architectural concept and meeting demanding railway loading, fatigue, and approval requirements.
The opportunity
sbp's alternative superstructure replaced the proposed flat steel hangers with CFRP tension members, allowing the hanger network and the surrounding structure to be considered together.
The engineering solution
Small components.
System-level consequences.
Carbo-Link manufactured the 88 CL SOLID CFRP hangers for the network arch. Their contribution extends beyond the weight of the hangers themselves.
Fatigue performance
CFRP's fatigue resistance supports compact tension-member sections for repeated railway loading.
Network behaviour
Hanger cross-section, axial rigidity and prestress influence load sharing and the behaviour of the arch and deck. Material selection is part of the structural design.
Handling & assembly
Low hanger weight simplified handling at the pre-assembly site and supported a short installation operation.
Project outcomes*
The practical lesson: assess the hanger system together with the arch, deck and construction sequence to understand the opportunity for the complete bridge.
≈500 t
Steel saved
≈1,350 t
Reinforced concrete saved
Only 4 days
Hanger installation
*Material savings reported by Empa for this bridge relative to the conventional steel-hanger solution. Installation duration reported by sbp. These are project-specific outcomes.
Recognition
Recognised for innovation,
engineering, and design.
-
Projects above £10 million · Bridge design & engineering
-
Road and railway bridges category
-
-
Institution of Structural Engineers
-
Technical summary
The project in detail.
Bridge
Location: Küstrin-Kietz, Germany – Kostrzyn, Poland
Opened: July 2024
Total superstructure length: 266 m
Main arch span: 130 m
Superstructure width: 13 m
Arch rise: 16 m
Rail tracks: 2
Design speed: Up to 120 km/h
Future electrification: Provision included
Dimensions follow sbp's published project data.
Carbon hangers
System: Carbo-Link CL SOLID CFRP hangers (CL-BRIDGE)
Quantity: 88
Diameter: 50 mm
Length range: 2.4 – 18.4 m
Axial rigidity EA: 300 MN
Working load: 1,960 kN
Breaking load: 3,600 kN
Dimensions follow Carbo-Link’s published project data.
Project team
Carbo-Link AG Carbon hanger manufacturer.
DB InfraGO AG Client / railway infrastructure owner.
Knight Architects Architecture and architectural concept development.
Schüßler-Plan General planning, alignment, foundations and substructures.
schlaich bergermann partner (sbp) Alternative superstructure design - carbon hanger network.
Empa Experimental fatigue testing and technical evaluation.
Sächsische Bau Principal contractor.
What could carbon hangers
change in your bridge?
Share your bridge type, span, loading requirements, design stage and programme.
We will review the hanger requirements and interfaces with your engineering team to assess a suitable scope.
Prefer email? info(at)carbo-link.com
Or to call? +41 58 201 25 00